7 marks
An R & D Project has certain activities to execute. First three of these activities include design (21), building prototype
5)and
evaluating equipment
7). The first activity does not have any
predecessor, but it is the predecessor of 2nd and 3rd activity. 4th
activity is testing of prototype
2), in which building of prototype is
the predecessor. Writing equipment report
5), method report
8),
and final report
2)are considered as 5th, 6th and 7th activities. 3rd
and 4th activities are the predecessor of 5th and 6th activity. 5th and
6th activities are the predecessors of 7th activity. Construct the
network diagram and indicate the critical path. The numbers in the
brackets indicate the time (in weeks) required for that particular
activity.