Q.1

14 Marks
(a)
3 marks
State and explain the purposes of estimating.
(b)
4 marks
Write a note on following.
1)Work charged establishment
2)Prime cost
(c)
7 marks

Determine the following quantity of items of works by considering given drawing figure -1 of a residential building.

GTU Engineering Economics, Estimation and Costing (3170615) Summer 2026 Question 1(c) Diagram
1)Earthwork in excavation for foundation.
2)Providing and laying P.C.C for foundation (1:4:8).
3)Brick Masonry work up to plinth level in C.M. (1:6).Consider height=0.15 m.Assume the width.

Q.2

14 Marks
(a)
3 marks
Define the term cash flow. Explain with sketch cash flow diagram
(b)
4 marks
Give the types of estimates and explain any one in detail.
(c)
7 marks

Define break-even point. Draw a break-even chart and write break-even analysis assumptions.

(c)
7 marks
Write a short note on time value of money.

Q.3

14 Marks
(a)
3 marks
Define Specifications and mention their objectives.
(b)
4 marks
What are the essential principles of good specification writing?
(c)
7 marks
Define Tender and give detailed classifications of tenders.
(a)
3 marks
Describe the factors affecting rate analysis.
(b)
4 marks
Write detail specifications for cement concrete (1:4:8) for foundation.
(c)
7 marks

Draft a tender notice for construction of Hospital, on behalf of R&B department, Government of Gujarat. The estimated cost of work is Rs. 10,32,58,000/-.

Q.4

14 Marks
(a)
3 marks
Write short note on schedule of rates.
(b)
4 marks
Calculate the material required for Cement concrete (1:4:8) for foundation for 10 m³.
(c)
7 marks
List and explain the essential requirements of a valid contract.
(a)
3 marks
What do you mean by Task or Out turn of work? How is it calculated?
(b)
4 marks
Calculate the material required for 12mm thick plaster in wall for 100m² (C.M. 1:4).
(c)
7 marks
Write note on:
1)Earnest Money
2)Security deposit.

Q.5

14 Marks
(a)
3 marks
Give the measurement units of the following:
1)Cement
2)Sand
3)Skirting
4)Bricks
5)Mild steel bars
6)Marble
(b)
4 marks
Differentiate between Estimating and Valuation.
(c)
7 marks
Explain the various types of outgoings.
(a)
3 marks
Define:
1)Cost
2)Price
3)Value.
(b)
4 marks
Distinguish between Book value and Market value.
(c)
7 marks
Explain the various types of rent. Figure-1 (All dimensions in Meter)
GTU Engineering Economics, Estimation and Costing (3170615) Summer 2026 Question 5 OR (c) Diagram

Preparing with friends?

Send this paper to your class group. Every question has its own link.

About this paper

Official Gujarat Technological University (GTU) examination paper and step-by-step solutions for Engineering Economics, Estimation and Costing (Summer 2026, B.E. · Civil Engineering, Sem 7). Features complete 70-mark regular & remedial examination pattern, official marking distribution across all 5 questions, and direct 1-click official PDF download.

Transcribed for student exam preparation from Gujarat Technological University official examination archives. Questions, syllabus guidelines, and curriculum marking schemes remain the intellectual property of Gujarat Technological University.

ViewDownload PDF